The First Phase of Roof Repairs has been completed

View of the restored roof.

This first phase of emergency roof and gutter repairs has cost the best part of £1 million. It has made most of the building watertight, but has probably tackled just over a third of the total roofing area.

The new roof above the old Board Room.
The new roof above the old Board Room.
The new roofs above the blacksmith's shop & pattern store.
The new roofs above the blacksmith’s shop & pattern store.
New roof and gutters now protects the erecting shop.
New roof and gutters now protects the erecting shop.